Checking and Testing Procedure

image_pdfimage_print

Checking and Testing Procedure

The following procedure will meet the key checking and testing requirements. Ensure that test results are recorded carefully. Other testing procedures may be used, provided that they meet the minimum requirements of the Wiring Rules.
It is also recommended that the tests be carried out whilst there is no electricity supply connected (except for the Fault Loop Impedance verification or the RCD operation test) to the installation, or, in the case of alterations to an existing installation, that the circuits to be tested have been isolated from the electricity supply and have been securely tagged
and where possible padlocked.